Flyover bridge in Sierakowice

In order to secure the existing bridge in the town of Sierakowice during the transportation of oversized loads destined for the power plant in Rybnik, a temporary bridge JSK450, 13.5m long, was used as a 'Flyover' type bridge, that is, a bridge over the existing bridge. Installed and dismantled several times in the same place for the duration of subsequent night crossings, it allowed for the safe passage of loads weighing several hundred tons.

Partager sur :

Détails du projet

Solution
Pont à poutres
Type
JSK-JBB
Longueur
13,5m + ramps
Poids
6m
Capacité
Super Heavy transports
Pont à poutres