JSK450 bridge to support chemical industry plant expansion

For our client building a prestigious and important investment for the Polish chemical industry in Police - HYUNDAI ENGINEERING CO., LTD. - we delivered the beam bridge JSK450 10.5m long. It will be used to support the construction site and allow movement of heavy equipment over pipe trenches that cut across the entire construction site. The design and delivery of the bridge were carried out at lightning speed - just 11 days - as requested by the client.

The integrated chemical complex Polimery Police will include propylene and polypropylene production installations, a transshipment and storage terminal and logistics infrastructure. The total estimated budget of the project is over EUR 1.5 billion (about PLN 6.5), making it the largest investment in the Polish chemical industry.

Share on:

Project details

Solution
Beam Bridge
Type
JSK-JBB
Length
10,5m
Width
3m
Height
0,45m
Weight
20t
Capacity
50t
Guardrail
BN4
Beam Bridge